Most Recent
Energy class action applicant slugged with $32M in costs for failed case
A judge has ordered the lead applicant in a failed class action against Queensland utilities Stanwell and CS Energy, which was slated to be worth $1 billion, to pay $32.4 million in costs.
Construction PRO
York Property loses appeal of $12.7M decision in dispute over Gold Cost high-rise
York Property has lost an appeal in a dispute with builder Tomkins over a payment claim for work on a Gold Coast high-rise, with the appeals court declining to set aside an adjudicator's decision that was later cut down to $12.7 million. 
Qld energy class action’s bid for evidence of $40M in defence costs meritless: judge
The applicant in a failed class action against Queensland utilities Stanwell and CS Energy can't get its hands on fee invoices as it prepares its response to a claim for recovery of what could be up to $40 million in costs.
Construction PRO
Qld developer of beachfront high-rise knocks back $10M ruling for builder
An adjudicator’s decision awarding $10 million to a builder on Queensland developer Heran Group’s high-rise luxury apartment building in Main Beach lacked procedural fairness after he went outside the parties’ submissions, a judge has found. 
Construction PRO
Judge ups Tomkins’ Midwater payment claim by $4.7M
Developer York Property is on the hook for an extra $4.7 million payment to the head construction contractor on the Midwater luxury residential high rise on the Gold Coast.
Construction PRO
Brisbane Airport can’t access PFAS info in $690M row with Airservices
Brisbane Airport has lost its bid for information about government-owned Airservices' handling of PFAS at other airports, in their $690 million dispute over use of the chemicals at the Queensland airport.
Construction PRO
Santos wins $690M against Fluor over Gladstone LNG project
Energy giant Santos has won a dispute over its Gladstone LNG project, described by a court as "litigation on a monumental scale", securing a $692 million judgment against engineering firm Fluor with the help of four silks.
Construction PRO
Developer can’t claim setoff in spat with Tomkins over $55M Sunshine Coast apartments
An appeal against a ruling that the developer of a $55M Sunshine Coast residential complex could not set off a liquidated damages claim against builder Tomkins' pre-completion payment claim has been thrown out.
Construction PRO
Judge extends freeze on $25M in Main Beach development spat
A developer has won an extension of a freeze on $25 million held in escrow in its dispute with a builder over payment claims for a Main Beach high-rise, after it filed an appeal.
Queensland energy class action can’t avoid defence costs pending appeal
A failed class action against Queensland utilities Stanwell and CS Energy can't delay payment of what might be in excess of $30 million in defence costs while it pursues an appeal, but has dodged a penalty for running a case the companies said was hopeless.