CWP probes BP’s purchase of Macquarie stake in Australian Renewable Energy Hub
BP's joint venture partner on one of the world's largest renewable energy projects has filed court proceedings seeking information  about BP's acquisition of Macquarie's stake in the project.
Construction PRO
‘Far-fetched and uncommercial’ take on PPAs rejected in spat over NT power plants
Electricity provider Rimfire Energy has prevailed in a fight with the builders of two power plants in the Northern Territory, winning $1.4 million in damages for a four-year delay in reaching target operating dates.
Construction PRO
Green hydrogen company Infinite Green Energy faces winding up bid
A judge has adjourned a creditor's winding up application against Perth-based green hydrogen company Infinite Green Energy, finding the delay could lead to a better outcome for creditors.
Construction PRO
Builder Kuatro fails in appeal in SOPA case against Elite Formwork
A court has ordered builder Kuatro Build to pay concrete subcontractor Elite Formwork more than $500,000 in progress payments for work on a Sydney development, finding no error in an adjudicator's determination.
Construction PRO
Court clarifies tax treatment for land development
A court has weighed in on the tax treatment of the proceeds of developed land, finding the landowner did not engage in business-like conduct such that his profits should be considered income.
Construction PRO
Developer can’t claim setoff in spat with Tomkins over $55M Sunshine Coast apartments
An appeal against a ruling that the developer of a $55M Sunshine Coast residential complex could not set off a liquidated damages claim against builder Tomkins' pre-completion payment claim has been thrown out.
Construction PRO
Major projects, subcontractors could be ‘imperiled’ if Roberts Co Victoria was liquidated: judge
A judge has given the Victorian unit of Roberts Co more time to put forward a deed of company arrangement that would save the builder from liquidation, noting liquidation could imperil its projects and subcontractors, who could not bring claims under the SOP Act if it was insolvent. 
Construction PRO
Special Gold liquidator can advance claims against Dyldam
A judge has ruled the liquidator of Special Gold can advance claims against Dyldam Developments, which the collapsed Sydney developer has called "hopeless".
Construction PRO
Kent Projects can’t escape fraud claims by CFMEU
The engineering company behind the world-first Kwinana energy transformation hub in WA has lost a bid to strike out fraud claims from a case by the CFMEU over an enterprise agreement covering maintenance workers.